Machine production

Shortening the decision time by 43 days for a factory

We identified gaps in environmental documentation and introduced a dialogue with the marshal's office. We accelerated the start of production by over a month.

-43 days of waiting
ClientTczew-Mech Sp. z o.o.
IndustryMachine production
TimelineMarch–June 2024

A machine factory in Tczew faced a wall of bureaucracy. The lack of an environmental decision blocked the opening of a new hall and the employment of 14 people. Kapituła Strategiczna took over talks with the office to unblock an investment worth PLN 1.2 million.

Technical dialogueGR AuditEnvironmental documentationAdministrative monitoring

The challenge

Tczew-Mech received 17 comments on the environmental impact report. Officials from Gdańsk suspended the procedure, and every week of delay generated PLN 12,400 in losses due to undelivered components to Germany. Communication between the plant and the marshal's office took place exclusively by letter, which extended each response by 12-14 business days. The company's board was close to resigning from expansion, fearing the loss of a key contract for 2025.

Our approach

We started with an audit of all collected documentation, which took us 4 days. We found an error in noise emission calculations, which was the main reason for rejections. Instead of sending more letters, we organized a working meeting at the office on April 12. We clarified technical doubts directly with the two inspectors leading the case. We translated engineering language into arguments understandable for public administration, which allowed avoiding a third round of corrections.

The solution

We delivered the corrected environmental report in 9 business days. We implemented a document flow monitoring system, calling the office every 48 hours to check the signature status. Kapituła Strategiczna took over all correspondence, thanks to which the production director could focus on machine assembly, not on studying the code of administrative procedure.

Results

By shortening formalities by 43 days, production at Tczew-Mech started on June 14. The company avoided contractual penalties and was on time with the first batch of goods for July 2024.

-43 days
shorter wait for signature
PLN 12,400
loss savings weekly
17
official comments clarified
14
saved jobs

Timeline

  1. March 2024
    Analysis of 17 errors in the environmental report.
  2. April 2024
    Working meeting at the Marshal's Office in Gdańsk.
  3. May 2024
    Submission of corrected technical documentation.
  4. June 2024
    Receiving a final administrative decision.

"To be honest, I thought it was another company for pretty presentations. However, Kapituła Strategiczna simply went to the office and handled the case with specifics. The decision arrived by mail faster than my plan assumed."

Mariusz Drzewiecki Production Director, Tczew-Mech Sp. z o.o. August 2024